ACC501 Assignment # 2
Answer:
i) Calculate the Payback Period for each project.
Initial Investment = 100,000
Payback Period for Project A:
In year one, 40,000 will be covered, and (100,000-40,000) = 60,000 should be covered.
In year two, further 25,000 will be covered, and (60,000-25,000) = 35,000 should be
covered.
In year three, 35,000 will be covered, which we have to cover from the project.
So, our payback period is 3 years for Project A.
Payback Period for Project B:
In year one, 45,000 will be covered, and (100,000-45,000) = 55,000 should be covered.
In year two, further 25,000 will be covered, and (55,000-25,000) = 30,000 should be
covered.
In year three, 20,000 will be covered, and (30,000-20,000) = 10,000 should be covered
yet.
In year four, 20,000 will be covered, but we have to cover 10,000 only,
So these 10,000 will take the time in years = 10,000/20,000 = 0.5 years
OR 10,000 will take the time in months = 10,000/20,000 * 12 = 6 months
OR 10,000 will take the time in days = 10,000/20,000 * 365 = 182.5 days
So, payback period for Project B is 3.5 years, or 3 years and 6 months or 3 years and
182.5 days.
ii) Calculate the Net Present Value (NPV) of each project.
NPV for Project A:
NPV = -Initial Investment +? Cash Flows / (1+r) t
NPV = -100,000 + [40,000 / (1+0.13) 1] + [25,000 / (1+0.13) 2] + [35,000 / (1+0.13) 3] +
[25,000 / (1+0.13) 4] + [20,000 / (1+0.13) 5]
NPV = -100,000 + [40,000 / (1.13) 1] + [25,000 / (1.13) 2] + [35,000 / (1.13) 3] +
[25,000 / (1.13) 4] + [20,000 / (1.13) 5]
NPV = -100,000 + [40,000 / 1.13] + [25,000 / 1.2769] + [35,000 / 1.442897] + [25,000 /
1.63047361] + [20,000 / 1.8424351793]
NPV = -100,000 + [35398.23] + [19578.67] + [24256.76] + [15332.97] + [10855.2]
NPV = 5421.83
NPV for Project B:
NPV = -Initial Investment + ? Cash Flows / (1+r) t
NPV = -100,000 + [45,000 / (1+0.13) 1] + [25,000 / (1+0.13) 2] + [20,000 / (1+0.13) 3] +
[20,000 / (1+0.13) 4] + [20,000 / (1+0.13) 5]
NPV = -100,000 + [45,000 / (1.13) 1] + [25,000 / (1.13) 2] + [20,000 / (1.13) 3] +
[20,000 / (1.13) 4] + [20,000 / (1.13) 5]
NPV = -100,000 + [45,000 / 1.13] + [25,000 / 1.2769] + [20,000 / 1.442897] + [20,000 /
1.63047361] + [20,000 / 1.8424351793]
NPV = -100,000 + [39823] + [19578.67] + [13861] + [12266.37] + [10855.2]
NPV = -3615.76
iii) Calculate the Internal Rate of Return (IRR) for each project.
Internal rate of return (IRR) is a rate where, NPV becomes zero let’s compute IRR for [LEFT]both projects,
No comments:
Post a Comment